9. Contract Account, Features of Contract Account, Cost-Plus Contract, Advantages, Disadvantages, Example Problems

9.1 Contract Account, Practical Problems and Solutions

In this article, we are going to discuss 9. Contract Account, Features of Contract Account, Cost-Plus Contract, Advantages, Disadvantages, Example Problems. Contract Account is a topic of Advanced Financial Accounting. It is an important topic included in final exam papers of all leading universities such as Punjab University, University of Sargodha, along with all major Indian Universities. Lectures with problem questions of the Company Final Account, Accounting Ratios, and, Consignment Accounts are already published on the site.

Contract Account

Contract is an agreement between two parties, one is called the contractor who executes or performs the job, and the other one is called the contractee for whom the job is done by the contractor. As a reward, the contractor receives the input cost of the project including his monetary benefit. In larger projects, the project is segmented into stages, and on each stage completion, the cost will be paid by the contractee after work certification. Contract Account is the account to record the contract activity.

Features of Contract Account

  1. In larger time frame-oriented projects, the project is segmented into smaller sub-projects.
  2. Work must be executed on the work site to perform the project
  3. A separate account must be maintained for billing and to track the work done.
  4. Direct costs such as material, labor, and overhead costs incurred in the project.
  5. The certificate of work done or work certified is used for billing.
  6. Retention money is given to the contractor after examining the quality of the work done on the project.
  7. In some cases, penalties are also imposed on the contractor if terms are decided prior the execution of the project.
  8. Risk factor is also involved in the contract.

Work in Progress

Work in progress is an important part of the contract account. It consists of two components, work certified and work uncertified. These both are placed on the credit side of the contract account and the Asset side of the balance sheet. Work certified is the certification of the work done according to standards.

Profit & Loss

In the case of profit, it is placed on the debit side of the contract account and further segmented into two parts, one is called profit, and the other part of profit is transferred to account reserve. The part of net profit is placed on the liability side of the Balance Sheet, whereas the Account reserve for contingencies part of the profit is subtracted from the Work certified and uncertified from the Asset side of the Balance Sheet. It is also placed on the debit side of the contract account along with profit.

How to calculate profit?

If the amount received from the contractee is not given, the total profit is multiplied by 2/3, and the work-certified percentage

If the amount received from the contractee is given, the total profit is multiplied by 2/3 and further multiplied by the quotient of the amount received by the contractee and the amount of work certified.

Cost-Plus Contract

A Cost-Plus Contract refers to a contract in which the amount paid is more than the cost incurred in the contract. In Cost-Plus, ‘cost” comprises all the direct, indirect, or overhead costs to the contract whereas “plus” means any extra amount over than cost that simply means profit. In simple words, Cost-Plus means the predetermined amount agreed upon between parties more than the incurred cost of the contract.

Components of a Cost-Plus Contract

There are three major components of a Cost-plus contract:

1. Direct Cost: Direct costs refers to all direct costs of material, labor, and other direct costs incurred in the project.

2. Overhead Cost: Overhead costs refer to all allocated costs that cannot be ascertained or identified with activity level such as rent of building, depreciation, utility expenses, etc.

3. Profit: refers to the percentage that is predetermined between parties and it is above than incurred cost of the contract.

Types of Cost-Plus Contracts

Only the contractor’s profit or fee component may be paid differently under the terms of the contract.

1. Price + Fixed Percentage: The contractor gets a percentage on the cost of the project.

2. Cost + Fixed Fee Contract: The contractor gets fixed fee that is independent to the cost of the project.

3. Cost + Fixed Percentage / Fee and Incentive: Under this condition, contractor not only fixed percentage but receive incentive in case of early completion of the project.

Factors of Success of Cost-Plus Contract

It depends on the system or frame work that is adopted prior to the execution of the project.

1. For verification of costs, efficient system should be adopted.

2. Proper communication between contractor and contractee about the project completion status must be present.

3. All terms and conditions about the project must be decided prior to the execution of the project to stay away from disputes.

4. The contractor must has sufficient money to complete the project.

5. To ensure the proper use of accounting, audit, and proper record maintenance, a team should be present to monitor the process.

Advantages

Benefits of cost-plus contracts include: 

  1. The Contractee is liable for the cost overrun and the contractor receives his agreed fee.
  • The quality of the project is not compromised but improves because the budget constraint is not the problem of the contractor.
  • The Contractor shall be fully aware of the costs incurred under the Project as he shall provide details of all costs when recovering costs from the Contractor.
  • The final cost of the project may be lower than the estimated cost, which benefits the contractor.
  • If material and labor costs are reduced, services are transferred to the contractor at the contractor’s cost.

Disadvantages

The disadvantages of cost-plus contracts are:

  1. If a contract or project is not completed within the period, the contractor may not get the funding of the contract.
  • In case of non-completion of the contract within the time agreed between the parties, the contractor may get penalties.
  • In the case of cost overruns, the contractor must provide a lot of additional evidence to justify the increase in project costs.
  • Disputes regarding reimbursement of costs may arise between the contractor and the client.
  • High costs are incurred in accounting, preparation of monthly reports, etc., to timely update about the contract progress and costs incurred on the contract.
  • Sometimes, projects take more time than expected time to complete the project.
  • There is uncertainty for the contractor because it is difficult to ascertain the final costs of the project.

Conclusion

Cost-plus contracts are most common in the construction industry, where the contractor is reimbursed as a contract profit for the number of expenses incurred on the contract and a percentage of the contract costs.

Example Problems for Understanding

Problem No 1:

The following were the expenditures on a contract for Rs. 600,000 commenced on 1-1-2010:

Material                                   Rs. 120,000

Wages                                      Rs. 164,400

Plant                                        Rs. 20,000

Business Charges                     Rs. 8600

Cash received on account to 31st December amounted to Rs. 240,000 being 80% of work certified; the value of materials on hand at 31st December was Rs. 10,000. Prepare an account showing the position at the end of the year and the proportion of the profit which might reasonably be taken to profit and loss account after 10% depreciation on plant.

Solution:

Contract Account

ParticularsRs.ParticularsRs.
Material120,000Work in Progress A/C 
Wages164,400Work Certified: 
Plant20,000(240,000/80)100300,000
Business Charges8600Closing Stock10,000
  Plant: 
  20,000×0.10=2000 
  20,000 – 2000=18,00018,000
Profit c/d15,000  
    
 328,000 328,000
Profit & Loss A/c Profit b/d15,000
(15,000 x 2/3)0.808000  
Work in Progress A/c   
(Reserve for Contingencies)7000  
 15,000 15,000

Problem No 2:

Arslan Construction Company Ltd. Have undertaken the construction of a building for Rs. 3,12,500, subject to a retention money of 20% which will be paid after six months of completion of contract. Following details are shown from the books of Arslan Company Ltd. On 31st December 2010.

Materials issued from store                                           Rs. 20300

Material Purchased                                                       Rs. 105000

Labor on site                                                                Rs. 101250

Depreciation on Plant Used during the year                    Rs. 3025

Overheads charged to the contract                                 Rs. 9275

Direct Expenses                                                            Rs. 5750

Amount of work certified                                              Rs. 275,000

Cash received from contractee                                       Rs. 220,000

Cost of work uncertified                                                Rs. 4125

Material on site on 31-12-2010                                      Rs. 1575

Accrued wages on 31-12-2010                                      Rs. 1950

Direct Expenses accrued on 31-12-2010                        Rs. 400

From the above figures prepare:

  1. Contract Account
  2. Contractee Account
  3. Show the relevant items as would appear in the Balance Sheet as on 31-12-2010.

Solution:

Contract Account

ParticularsRs.ParticularsRs.
Materials issued from store20300Work in Progress 
Materials Purchased105000Work Certified                 275000 
Labor on site101250Add work uncertified        4125279125
Depreciation on Plant3025Materials at site Closing1575
Overhead Charges9275  
Direct Expenses5750  
Accrued wages1950  
Direct Expenses Accrued400  
    
Profit c/d33,750  
 280,700 280,700
Profit & Loss A/C: Profit b/d33,750
(33750 x 2/3)220,000/275,000 or 80%18,000  
Balance c/d (Contingencies)15750  
    
 33,750 33,750

Contractee Account

ParticularsRs.ParticularsRs.
Balance c/d220,000Cash A/c220,000
    
 220,000 220,000

Balance Sheet

As on December 31st 2010

LiabilitiesRs.AssetsRs.
Profit & Loss A/c18000Work in Progress: 
Outstanding Direct Expenses400Work Certified                                         275000 
Outstanding Wages1950Add work uncertified                                4125 
  Less Profit c/f                                          (15750) 
  Less Cash Received from Contractee    (220,000)43375
  Materials on hand1575

Problem No 3:

A firm of builders, carrying out large contracts, kept in a contract ledger, separate accounts for each contract. On 30th June, 2010 the following was shown as being the expenditure in connection with Contract No. 555.

Material Purchased                                           Rs. 58063

Material from stores                                         Rs. 9785

Plant which had been use on other contracts       Rs. 12523

Additional plant purchased                                Rs. 3610

Wages                                                              Rs. 73634

Direct Expenses                                                Rs. 2026

Proportion of establishment charge                    Rs. 8720

The contract, which was commenced on 1st Feb, 2010, was for Rs. 300,000 and the amount certified by the Architect, after deduction of 20 percent retention money was Rs. 120,800, the work being certified to the 30th June, 2010. The materials on the site at that date were valued at Rs. 9858.

A contract plant Ledger was also kept, in which depreciation was dealt with monthly; the amount debited in respect on plant on Contract No 555 to 30th June, 2010 was Rs. 1130.

You are required to prepare an account showing the profit on contract to 30th June 2010.

Solution:

Contract Account

ParticularsRs.ParticularsRs.
Materials issued from store9785Work in Progress 
Materials Purchased58063Work Certified    \frac{120800}{80}(100)\  151000
Wages73634Materials at site Closing9858
Depreciation on Plant1130  
Establishment Charges8720  
Direct Expenses2026  
    
Profit c/d7500  
 160858 160858
Profit & Loss A/C: Profit b/d7500
(7500 x 2/3)0.804000  
Balance c/d (Contingencies)3500  
    
 7500 7500

Problem No 4:

A building contractor, having undertaken construction work at a contract price of Rs. 750,000 began the execution of work on 1st Jan, 2010. The following are the particulars of contract up to 31st Dec. 2010:

Machinery installed at site                                 Rs. 45,000

Materials Sent to site                                         Rs. 256047

Labor at site                                                     Rs. 223125

Direct Expenses                                                Rs. 9501

Overhead charges allocated                               Rs. 12378

Materials returned from site                              Rs. 1647

Work certified by architect                                Rs. 585,000

Cash Received                                                  Rs. 540,000

Cost of work not certified yet                            Rs. 13,500

Materials on hand on 31-12-2010                       Rs. 5649

Wages accrued on 31-12-2010                          Rs. 8070

Value of machinery on 31-12-2010                    Rs. 33,000

It was decided that the profit made on the contract in the year should be arrived at by deduction the cost of work certified from the total value of the architect’s certificates, that 1/3 of the profit so arrived at should be regarded as a provision against contingencies, and that such provision should be increased by taking to the credit of the Profit and Loss Account only such portion of the 2/3 profit as the cash received bore to the work certified.

Solution:

Contract Account

ParticularsRs.ParticularsRs.
Machinery Installed45000Work in Progress 
Materials256047Work Certified     585000\
Labour223125Add Uncertified    13500598500
Direct Expenses9501Materials at site Closing5649
Overhead  Charges12378Machinery Closing33000
Wages Accrued8070Materials Returned1647
    
Profit c/d84675  
 638796 638796
Profit & Loss A/C: Profit b/d84675
  \left( 84675\ x\frac{2}{3} \right)(\frac{540000}{585000})\  52108  
Balance c/d (Contingencies)32567  
    
 84675 84675

Problem No 5:

S & S Ltd are contractors for the construction of a pier for the Seaform Development Company. The value of the contract is Rs. 300,000 and payment is by engineer’s certificate subject to retention of 10% of the amount certified; this is to be held by the Seafront Development Company for six months after the completion of the contract.

The following information is extracted from the records of S and S Ltd.

Wages on site                                                               Rs. 41260

Materials delivered to site by supplier                            Rs. 58966

Materials delivered to the site from store                        Rs. 10180

Hire of plant                                                                 Rs. 21030

Expenses charged to contract                                        Rs. 3065

Overhead charged to contract                                        Rs. 8330

Materials on site on 30th September 2010                      Rs. 11660

Work certified                                                              Rs. 150,000

Payment received                                                         Rs. 135,000

Work in progress (not the subject of a certificate to date) Rs. 12613

Wages accrued on 30th September 2010                         Rs. 2826

Materials costing Rs. 3384 was damaged and had to be disposed off for Rs. 884

Required: Prepare Contract Account and Work in Progress Account in the books of contractor, also shows the relevant items as would appear in the Balance Sheet.

Contract Account

ParticularsDr. Rs.ParticularsCr. Rs.
Materials delivered to site by supplier58966Material Closing11660
Materials delivered to the site from store10180Work in Process: 
Hire of plant21030Work Certified       150,000 
Wages on site          41260 Work Uncertified     12613162613
Add Outstanding     282644086Loss of Material3384
Expenses charged to contract3065  
Overhead charged to contract8330  
Profit c/d32,000  
 177657 177657
Profit & Loss Profit b/d32,000
(32,000 x 2/3)0.9019200  
Work in Progress (Reserve)12800  
    
 32,000 32,000

Work in Progress Account

ParticularsDr. Rs.ParticularsCr. Rs.
Contract Account: Contract Account: 
Work Certified       150,000 Reserve for contingencies12800
Work Uncertified     12613162613Balance c/d149813
    
 162613 162613

Balance Sheet

As on 31st December 2010

Liabilities   Rs.AssetsRs.
Wages Accrued2826Material on site closing11660
Profit & Loss A/C              19200 Work in Progress: 
Less Loss of Material         (2500)16700Work Certified              150,000 
  Add Work Uncertified     12613 
  Less Cash received      (135,000) 
  Less Reserve                (12800)14813
  Cash884

Problem No 6:

X Ltd. Was awarded a contract to build an office block in Lahore and work commenced at the site on 1st March 2010.

During the period to 31st December 2010, the expenditures on the contract were as follows:

Materials issued from stores                              Rs. 94110

Material Purchased                                           Rs. 280,700

Direct Expenses                                                Rs. 61490

Wages                                                              Rs. 184,930

Charges made by the company for administration expenses Rs. 21460 plant and machinery purchased on 1st March, for use at site Rs. 121800

On 31st December 2010, the stock of material at site amounted to Rs. 21640 and there were amount outstanding for wages Rs. 3660 and direct expenses Rs. 490

X Ltd. Has received on account the sum of Rs. 641700 which represents the amount of Certificate No 1 issued by the architects in respect of work completed to 31st December 2010, after deducting 10% retention money.

The following relevant information is also available:

  • The plant & machinery has an effective life of five years, with no residual value and;
  • The company only takes credit for two-third of the profit on work certified.

Required: Prepare a contract account, work in progress account, and show the items appeared in Balance Sheet of X Ltd. on 31st December, 2010.

Solution:

Contract Account

ParticularsDr. Rs.ParticularsCr. Rs.
Materials from store94110Material Closing21640
Materials purchased     280700Work in Process: 
Direct Expenses            61490 Work Certified & Uncertified       
Add Outstanding              49061980 \left( \frac{641700}{90} \right)100\  713000
Wages                     184930   
Add Outstanding         3660188590  
Depreciation on Plant & Machinery   
  \frac{121800 - 0}{5} = 24360,\ \left( \frac{24360}{12} \right)10\ 20300  
Administrative Expenses21460  
Profit c/d67500  
 734640 734640
Profit & Loss Profit b/d67500
(67500 x 2/3)0.9040500  
Work in Progress (Reserve)27000  
    
 67500 67500

Work in Progress Account

ParticularsDr. Rs.ParticularsCr. Rs.
Contract Account: Contract Account: 
Work Certified & Uncertified713,000Reserve for contingencies27000
  Balance c/d686000
    
 713000 713000

Balance Sheet

As on 31st December 2010

Liabilities   Rs.AssetsRs.
Outstanding Wages3660Material on site closing21640
Outstanding Direct Expenses490Work in Progress: 
Profit & Loss A/C             40500Work Certified & uncertified 713000            
  Less Profit c/f                        (27,000) 
  Less Cash received               (641700)44300
  Machinery                          121800
  Less Depreciation               (20300)101500

Consignment Account, Consignor or principal, Consignee or agent, Complete Analysis with Journal Entries, Theoretical Aspect, MCQ’s and Practical Examples

Analysis of Accounting Ratios, Liquidity Ratios, Profitability Ratios, Solvency Ratios, Efficiency Ratios, Market Ratios, Return on Investment Ratios, Different Ratios and their Formulas, Practice Questions for Understanding

Analysis of Accounting Ratios, Exercise Problem Questions & their solutions

4: Company Final Accounts, Trading Profit & Loss Account, Income Statement, Profit & Loss Appropriation Account, Statement of Financial Position or Balance Sheet, with examples for understanding

4.1: Company Final Account, Exercise Problems and their solutions

  1. Material Costing, Specific Identification Method, Weighted Average Cost Method, First In, First Out Method(FIFO), Last In, Fist Out Method(LIFO)
  2. Material Costing, Economic Order Quantity EOQ, Reorder Point/Ordering Point, Lead Time, Maximum Level of Inventory, Minimum Level of Inventory, Average Stock Level, Safety Stock, Danger Level, Optimum number of Orders, Order Frequency

Leave a Comment

Your email address will not be published. Required fields are marked *